Purchase order versus goods receipt
A purchase order says what you asked the supplier to deliver. A goods receipt says what the supplier actually delivered on a specific receipt event. Keeping them separate allows one PO to have partial receipts, damaged quantity, on-hold quantity, multiple delivery dates, and a remaining outstanding balance.Receive a partial delivery
1
Open the purchase order
Review the ordered lines and quantities before recording the delivery.
2
Create a goods receipt
Start the receipt flow linked to the purchase order.
3
Enter the delivered quantities
For each line, enter accepted, damaged, or on-hold quantity as appropriate. Lynka calculates the total received quantity from those buckets.
4
Save the receipt
Save the goods receipt with its receipt number and dates.
5
Post when ready
Posting locks the receipt for normal editing and applies the supported inventory and accounting consequences. If the remaining PO quantity is greater than zero, the order can stay partially received.